In addition, the prototyped use cases shall also be of value for the countries who designed and provide these. For this purpose, we envision a person from the country (as a country representative or dedicated proxy) to follow the use case through the different processing steps (Service Design, Generalization to Reference Use Case by PC, Sequencing by TC, Modelling and prototyping by Sandbox team) following the principles of collaboration and early involvement.

Prioritization

The country representative (or proxy) shall inform the partners about different options for prototypes and guide the focus of the prototype development based on the value proposition he/she sees for the country by prototyping the use case. The focus could look like as follows:

...

  • With the given resources, it is impossible to implement a country use case in an end-to-end and fully functional manner (frontend + backend).

Implementation

Phase 1: Business Analysis

Prerequisites:

  • Prioritization is defined (see above)

Fixed time box: 2 sprints (1 month)

Participants: UX Designer, Business Analyst, Country Representative

Deliverable: BPMN Diagram of the to be implemented use case steps (example: USCT MVP)

Phase 2: Development

Prerequisites:

  • BPMN Diagram

  • Needed BB candidate applications integrated in Sandbox environment

Fixed timebox: 4 sprints (2 months)

Participants: Full Stack of Gofore Developer Team, Country Representative

Deliverable: Use Case Prototype according to the agreed prioritization. The functional scope is based on what the team can deliver in the given time box