Scope of work as of April 21st, 2024
The change in scope responds to the country´s request to enable the use of the eCabinet solution for the 25 government entities.
Phase | Description | Responsible entity |
---|---|---|
1 6 months Feb - Jul 2024 | e-cabinet.gouv.dj - IP web ware decides which one to use One system, with one unit per government entity. Each entity will have its own users. This setup, facilitates scalability. | IGDC: ITU, MENI, ANSI, PM, Urban & Planning |
2 | Integration of Webware with ID, Digital signature using x-road? | MENI with responsible entities, & systems integrators |
Scope of work as of April 15th 2024
Phase | Description | Responsible entity |
---|---|---|
1 6 months Feb - Jul 2024 | Correspondence between MENI, PMO and Urban and Planning using xRoad. | IGDC: ITU, MENI, ANSI, PM, Urban & Planning |
2 | Integration of Webware with ID and Digital signature. | MENI with responsible entities, & systems integrators |