Open RFP - Procurement Status

GovStack-ITU Micro Procurement Status

Major Milestones

PAYBB

IDVBB

IMBB

REGBB

 

Status

Completed on/

To be completed by

Status

Completed on/

To be completed by

Status

Completed on/

To be completed by

 

RFP Publication date

Completed

28th Apr 22

Completed

13th May 22

Completed

03rd Jun 22

On Hold

URL

Inactive

https://www.ungm.org/Public/Notice/173355

Active

https://www.ungm.org/Public/Notice/174171

Active

https://www.ungm.org/Public/Notice/175569

NA

Submission of answers to clarification questions by ITU

Completed

02nd Jun 22

Completed

17th Jun 22

In progress

08th Jul 22

NA

Deadline for submission of proposals by bidders

Completed

23rd Jun 22

In progress

14th Jul 22

To start

05th Aug 22

NA

Technical Evaluation & its report submission

In progress

27th Jul 22

To start

19th Aug 22

To start

19th Aug 22

NA

Estimated contract signature

To start

3rd Week of Aug 22

To start

Sep 22

To start

Sep 22

NA